PUBLIC STATEMENT ( By South Dublin County Council)
Progress report on Poddle and Camac river flood alleviation schemes under Eastern Region Catchment Flood Risk Assessment & Management Study (CFRAMS).
The Rivers Poddle and Camac form part of the Eastern RBD (River Basin District) Catchment Flood Risk Assessment & Management (CFRAM) Study.
Severe flooding was experienced on both rivers in October 2011. A meeting was held in the Civic Offices at 11am this morning (20/1/2012) to discuss the current programme for delivery of the Poddle and Camac catchment studies under the Eastern CFRAM Study. Dublin City Council, South Dublin County Council, The Office of Public Works and the Consultants for the Eastern CFRAM Study were represented.
Under the current programme, flood maps for the Poddle and Camac catchments are due for completion in December 2013, with the full Catchment Flood Risk Management Plan due for completion in December 2015. Any flood relief schemes recommended from this plan are likely to be subject to a national programme of centrally-prioritised flood relief works, and could possibly take another three to five years to implement following consulting engineer, planning and contractor procurements. This would estimate the earliest date for completion of any feasible works by 2019 to 2020.
The purpose of the meeting was to examine the possibility of completing catchment modelling and works identification for the Poddle and the Camac at the earliest possible date, and to explore options for expediting some flood relief works on these rivers.
Following a very constructive discussion by all parties, it was agreed that, subject to final agreement on the scope of the technical analysis and modelling approaches:
• The survey work had commenced with likely completion on both rivers by March 2012.
• Modelling could proceed thereafter, provided sufficient technical resources are in place to ensure that it does not compromise the overall Eastern CFRAM programme, and subject to agreement on funding.
• The results from the previous Greater Dublin Strategic Drainage Study for the Poddle and Camac may be exploited to assist in advancing the modelling in line with the national CFRAM standards.
• Any works identified could proceed in advance of CFRAM Study completion provided they did not negatively impact on the recommendations of the overall CFRAM Study, and subject to technical approval, environmental assessment and compliance with OPW flood scheme requirements (Such works likely to Proceed using Part 8 procedure).
• Repairs to existing damaged walls would form part of the baseline of the modelling assessment.
• Any emergency or minor works should be kept a minimum so that they do not negate a more long-term solution that would give a greater benefit to the citizens of Dublin.
A further meeting will take place in February with a view to assessing technical proposal.